RAF Honington LED Upgrade

Brief:

Sacx was tasked with replacing the existing lighting at the Headquarters with LED fittings as part of a broader sustainability initiative.

What We Did:

We conducted a comprehensive building survey to ensure the correct quantity and specifications of light fittings were provided. To minimize disruption to the building’s occupants, we worked in a systematic manner, allowing for smooth project scheduling. Over the course of the project, Sacx replaced approximately 200 light fittings.

Challenges Overcome:

Due to the nature of the building and its security requirements, careful planning was essential. Sacx coordinated closely with the client’s Project Manager and the building custodian to schedule the work in alignment with the occupants’ needs and security protocols.

Client:

MOD / Vivo Defence Services

Sector:

Commercial, MOD

Divisons:

Electrical

Location:

RAF Honington

Project:

LED Upgrade

Value:

£37k

Timescale:

2 Weeks